• Text Size:
  • A
  • A
  • A

Lowcountry Celebration Park (Coligny Area Redevelopment Initiative)

Project Details
Status:   Under Construction   Under Construction Icon

Project Area Map

Project Description

Lowcountry Celebration Park includes: a large lawn and stage to accommodate festivals, concerts and other gatherings; a destination playground with an iconic ship playground; the Sandbox Children's Museum; walking trails and boardwalks; exercise stations; additional parking and; improved access to Beach Parking. The park is located between the Circle Center Shopping Center and the Beach Parking lot at the end of Pope Avenue.

Related CIP Project:

Coligny Area Road Improvements


On March 4, 2014 Town Council passed a resolution directing staff to engage a consultant to prepare a concept plan for the Coligny area and the Planning Commission to develop a recommendation to Town Council on the plan. On April 2, 2014 the Planning Commission convened a Public Workshop for the purpose of gathering input regarding a destination park and playground, surface parking, children's museum, streetscape improvements, roadway and intersection improvements, and pedestrian improvements. The results of the public workshop along with a list of "quick action" items were presented at a follow-up meeting on April 23, 2014.

During the summer of 2014 the Town's traffic consultant, SRS Engineering, conducted both traffic and parking counts and made recommendations for improvements in the Coligny District as well as the Pope Avenue corridor. The recommendations address enhancement of operations for vehicles and pedestrians as well as potential new roadway connections providing alternate routes and connectivity through the planning area.

Based on the public and Planning Commission input and in conjunction with the traffic and parking assessments, the consultant team prepared a Conceptual Master Plan for improvements within the Coligny District.

The Conceptual Master Plan focused on 6 primary elements.

  1. Roadway and Intersection Improvements including Nassau Street extension, Lagoon Road signalization and extension, realignment of the parking lot entrance, and the addition of a signal on South Forest Beach Drive;
  2. Surface Parking including +/- 553 permanent parking spaces in the parking lot and on-street parking which represents an increase of +/- 137 permanent usable parking spaces;
  3. the creation of a Destination Park and Playground including a central event space for passive and event use, a perimeter trail network with exercise stations and interpretive signage/experiences, a bandshell/pavilion, restroom/shelter with drop-off, and an adventure playground that is lowcountry and nature themed with separate areas for different age groups;
  4. a Children's Museum with +/- 3,500 sf indoor museum space and +/- 1,500 sf outdoor play space adjacent to dedicated parking;
  5. Streetscape Improvements on Pope Avenue and South Forest Beach Drive;
  6. and Pedestrian Improvements including new leisure trails and enhanced pedestrian crossings.


Project Objectives

Public sector investment to spur private redevelopment.

Additional Documents


 
Hilton Head Island - Coligny Area Park & Transportation Projects
Public group
Join Facebook Group
 
Subscribe to Updates
e-subscription iconTo sign up for email updates, enter your email address below.


Projected Construction Start Date:  Spring 2019

Estimated Completion Date:  Fall 2020

Project Engineer:  Thomas & Hutton

Project Architect:  

Watson Tate Savory
Wood+Partners Inc. (Lead Consultant/Landscape Architect)

Construction Contract Awarded To:  Nix Construction

Funding Sources:  TIF

Estimated Cost of Project:  +/- $12,000,000 phase 1 construction, not including property

Project Manager:  

Chris Darnell email icon, Urban Designer, 843-341-4676


Project Updates
  • 1/27/2020 -
    • Work continues on the restroom building in a push to open it as soon as possible.
    • The additional parking at the beach parking lot is on schedule to open by St. Patrick's Day.
    • The contractor will be working on the Nassau sidewalk so that it will be open for use as soon as possible.
    • The timber frame for the Children's Museum is up.
    • Concrete footers are in place and foundations poured in the playground. The ship mast have been delivered to the site. Construction of the ship will begin the first of February. See the Facebook post of the pre-assembled ship during inspection in the factory.
    • The pavilion is the critical path item for completion of the park. The timber frame for this building is expected to go up the last part of February.
  • 11/21/2019 -
    • The lagoon is 2 feet below the designed water level.
    • Setting Sun has been installed and work continues on the boardwalks, pond pavilion and retaining wall.
    • The clearstory on the restroom building will soon be constructed.
    • Curb work on the adjacent parking area is complete with installation of the asphalt drive aisle and paver parking to follow.
    • The pavilion is the critical path item for completion of the park and the footers for that structure have been installed.
    • The ship in the playground has been pre-assembled at the factory. It will be taken apart in sections for ease of installation in February.
  • 10/28/2019 -
    • Rough grading of the site has been completed.
    • Park storm drains have been installed.
    • Piles for the boardwalks, pond pavilion, bridge and retaining wall have been driven.
    • Block work on the restroom building is complete and the timber for this structure has been delivered.
    • The museum foundation is complete.
    • The band shell pavilion foundation is about 50% complete.
    • The Setting Sun sculpture will be installed the first of November before the lagoon is flooded.
    • Work should begin in November on the parking at the Lagoon Road entrance.
  • 10/21/2019 - The foundations being laid for the new Sandbox Children’s Museum building.
  • 10/18/2019 - Piles for the boardwalks, lagoon pavilion, sculpture and retaining wall are being driven in the dry lagoon. This process should be complete by the end of this month at which time the pumps will be turned off and the lagoon will fill with water.

Project Photos & Videos
  • Photo of Sandbox Childrens' Museum Construction
    Sandbox Childrens' Museum Construction - 1/20/2020
  • Photo of Sandbox Childrens' Museum Construction
    Sandbox Childrens' Museum Construction - 1/15/2020
  • Photo of Construction of the restroom building
    Construction of the restroom building - 12/17/2019
  • Photo of The bulkhead at “Setting Sun”
    The bulkhead at “Setting Sun” - 12/17/2019
  • Photo of Form work for the wading pool feature in “Adventure Playground”.
    Form work for the wading pool feature in “Adventure Playground”. - 12/17/2019
  • View More Photos...