• Text Size:
  • A
  • A
  • A

Fire Station 2 Replacement

Project Details
Status:   Under Construction   Under Construction Icon

Project Area Map

Project Description

This Fire Station replaces the original building which was built in 1976. The original station and property has been modified/renovated numerous times through the years. The building is old, inadequate and suffering from chronic water damage, wood rot, and structural weakness.

As part of the Town’s initiative to upgrade facilities, a standard design for Town Fire Stations was developed in the late 1990's. The design includes the ability to withstand some seismic and high wind events and that the stations are built as high as possible due to storm surge and the ability to house additional staff in an extreme emergency. Construction of Fire Station No. 2 should start in September 2016 and will be LEED silver certified. The station is about 8,500 sq. ft. has sleeping facilities for 5 firefighters, a community meeting and training room, weight room, and three bays for fire apparatus and ambulances.

Fire Station No.2 serves Sea Pines.



Projected Project Schedule:  

Projected Construction Start Date:  Pending

Estimated Completion Date:  18 months after notice to proceed

Project Engineer:  Alliance Consulting Engineers, Inc.

Project Architect:  Rosenblum Coe Architects, Inc.

Construction Contract Awarded To:  To Be Determined

Funding Sources:  Hospitality Tax

Estimated Cost of Project:  $3.8 million

Project Manager:  

Julian Walls email icon, Facilities Manager, 843-342-4587


Project Updates
  • 8/12/2020 - The new Fire Station #2 masonry is still underway. The main building and apparatus bay footings have been inspected and anchor bolts placed. Walls in both areas are also being erected and plumbing is being installed prior to the foundation being poured. The station is still on schedule for May of 2021.
  • 3/17/2020 - With the pre-clear site inspection complete, Demolition on the old station started yesterday, 3/16/2020 and is scheduled to be completed by 4/3/2200. The project thus far, is on schedule.
  • 1/21/2020 - A contract was signed with Nix Construction on 1/15/2020 . The contract amount is $3,783.600 and the contractor has 420 calendar days to complete. A notice to proceed is expected in or around mid-February. The first phase of the new station will be demolition and should not interfere with the RBC Heritage.
  • 10/7/2019 - Fire Station 2 replacement is back on the calendar. The design basically is staying the same with minor elevation and code updates. The Sea Pines ARP has approved the re-submittal and Town staff comments are complete. Bidding documents are being fine-tuned and a RFP is expected mid-November with a notice to proceed anticipated at the first of the year.
  • 8/23/2017 - Issuance of a revised Request for Proposal was put on-hold due to the impacts of Hurricane Matthew and remains on-hold indefinitely pending funding direction from the Town Manager and Town Council.

Project Photos & Videos
  • Photo of Fire Station 2 Construction
    Fire Station 2 Construction - 8/10/2020
  • Photo of Fire Station 2 Construction
    Fire Station 2 Construction - 7/27/2020
  • Photo of Fire Station 2 Construction
    Fire Station 2 Construction - 7/16/2020
  • Photo of Fire Station 2 Construction
    Fire Station 2 Construction - 6/2/2020
  • Photo of Fire Station 2 Demolition
    Fire Station 2 Demolition - 3/17/2020
  • View More Photos...