Coligny Area Roadway Improvements

Project Details
Status:   Complete   Complete Icon

Project Area Map

Project Description

(Nassau Street, South Forest Beach, Lagoon Road Extension, Pope/Lagoon Intersection-Traffic Signal)

Various Roadway Improvements – new traffic signal at Pope-Lagoon, improved turn lanes on Pope Avenue, extending Lagoon Road into new park and adding on-street parking.

Pathway Reconstruction along Tanglewood Drive, and a new pathways along the Oceanside of South Forest Beach Drive from Coligny Beach Park to Tanglewood Drive.

Related CIP Project:

Lowcountry Celebration Park (Coligny Area Redevelopment Initiative)

Project Objectives

To improve traffic and pedestrian capacity and safety and support other public projects and economic development in this initiative area.

Additional Documents


 
Hilton Head Island - Coligny Area Park & Transportation Projects
Public group
Join Facebook Group
 
Subscribe to Updates
e-subscription iconTo sign up for email updates, enter your email address below.


Projected Project Schedule:  

Design/Permitting: Summer 2015 - Spring 2016

Projected Construction Start Date:  September 2018

Estimated Completion Date:  October 2019

Project Timeline
Pope Avenue Resurfacing Draft Paving Schedule

Project Engineer:  Thomas & Hutton Engineering Company

Construction Contract Awarded To:  Quality Enterprises

Funding Sources:  TIF

Estimated Cost of Project:  $4.82 million

Project Manager:  

Jennifer Lyle email icon, Assistant Town Engineer, 843-341-4779


Project Updates
  • 10/31/2019 - Tanglewood Drive will be closed at Nassau Street on Thursday, October 31st from approximately 7 am to 7 pm, as crews replace a segment of pipe for completion of the Coligny Roadway projects on Nassau Street.
  • 10/14/2019 -
    • Nassau Street paving, new water and sewer for the Lowcountry Celebration Park, and storm sewer installed
    • Pervious parking spaces on Nassau Street completed; Pathway reconstructed on Nassau Street from Tanglewood Drive to crossing at Circle Center
    • Stamped asphalt crosswalks installed along Pope Avenue and Nassau Street; Stamped asphalt crosswalks at Pope Ave and Cordillo Parkway to be completed by the end of October 2019
    • Traffic signal mast arms at Pope and Lagoon installed; New Traffic signal to be activated by the end of October 2019 at Pope Ave and Lagoon Road
    • Final permanent pavement markings along Pope Ave to be completed by the end of October 2019
  • 10/9/2019 - The Town's contractor is completing the Coligny Area Roadway and Pope Avenue Resurfacing work. Here is a timeline of activities scheduled for this week and next week:
    • Stamped crosswalks at Pope Avenue and Cordillo Parkway will be worked on and completed between 7 pm, Wednesday, October 9 and 7 am, Thursday, October 10.
    • Stamped crosswalks at Pope Avenue and Lagoon Road and Pope Avenue at Coligny Circle are to be constructed between 7 pm, Thursday, October 10 and 7 am Friday, October 11, and 7 pm, Friday, October 11 and 7 am, Saturday, October 12.
    • Traffic signal work will continue the week of October 14 - 19. We will send a notice letting you know when the signal will be activated.

    The following activities were completed earlier this week:

    • Stamped crosswalks on Nassau Street were completed on Tuesday, October 8.
    • New traffic signal mast arm and poles were installed earlier this week at Pope Avenue and Lagoon Road.
  • 10/7/2019 - Expect Pope Avenue Lane Closures During October

    Through the end of October, there will be intermittent lane closures along Pope Avenue while the Town of Hilton Head Island's contractor completes the Coligny Area Roadway and Pope Avenue Resurfacing projects.

    The intermittent lane closures will be necessary to complete the following work:

    • Installation of new traffic and pedestrian signals at the intersection of Pope Avenue and Lagoon Road.
    • Landscaping on medians and shoulders.
    • Placement of permanent pavement markings along Pope Avenue including decorative, stamped crosswalks at Cordillo Parkway and Lagoon Road.
    • Asphalt repairs along Pope Avenue.
  • 6/14/2019 - As we wrap up our work on the Coligny Area Roadway and Pope Avenue Resurfacing Projects for the summer, we thank you for your patience. Work on Pope Avenue is stopped for the summer with the exception of removing and replacing the sections of rippled or wavy surface pavement. We are still working with the SC Department of Transportation to resolve this matter and will notify you when this work is scheduled. Work will continue through July on Nassau Street. Rain delayed the paving on Lagoon Road this week; it is now scheduled to occur one night during the week of June 17. Work has also started on the Town's Lowcountry Celebration Park. Thank you to all who joined us on Tuesday for the groundbreaking ceremony for this project, scheduled to be completed in summer 2020.

    What Happened the Week Ending June 14, 2019

    • Stormwater installation connection at Nassau Street between Pope Avenue and the first Circle Center driveway.
    • Started grading on Nassau Street and storm water pipe connection from Tanglewood Drive to Nassau Street.
    • Concrete formed to connect the pathway along Pope Avenue from the parking lot entrance to Coligny Circle.

    What's Happening the Week of June 17, 2019

    • Paving of Lagoon Road to tie into Pope Avenue. This is scheduled to occur between 10 p.m. and 9 a.m. on Tuesday, June 18 and Wednesday, June 19, weather permitting.
    • Completion of the pathway connection along Pope Avenue from the parking lot entrance to Coligny Circle.
    • Curb installation on Nassau Street and drainage installation on Nassau Street and Tanglewood Drive.
    • Sanitary sewer and water line installation to begin on Nassau Street. Affected customers will be notified in advance of any planned service disruptions.

Project Photos & Videos
  • Photo of New Signal at Pope Ave and Lagoon Road Intersection
    New Signal at Pope Ave and Lagoon Road Intersection - 12/19/2019
  • Photo of New Signal at Pope Ave and Lagoon Road Intersection
    New Signal at Pope Ave and Lagoon Road Intersection - 11/18/2019
  • Photo of Milling Remediation on Pope Ave
    Milling Remediation on Pope Ave - 11/11/2019
  • Photo of Reconstruction of Nassau Street Pervious Parking
    Reconstruction of Nassau Street Pervious Parking - 10/17/2019
  • Photo of Installation of Parking on Nassau Street
    Installation of Parking on Nassau Street - 9/16/2019