Media Release

2016 Beach Nourishment Project - Progress Update

Release Date: November 28, 2016

Contact Information:
Scott Liggett, PE email icon , Director of Public Projects & Facilities, 843-341-4776, Fax: 843-842-8587


On November 27, 2016, after relocating the dredge, pipeline and equipment the Town's contractor Weeks Marine, Inc. restarted sand placement activities near Singleton Beach. Work will advance southward along the Palmetto Dunes oceanfront to near Captain's Walk. In order to finish the project, approximately 600,000 cubic yards of sand is to be placed along about 10,000 feet of shoreline. The project is expected to be concluded in late December. Additional Beach Renourishment Project information is available at the Town's website: www.hiltonheadislandsc.gov.