Mathews Drive Side Streets Project

The Mathews Drive Side Streets project is part of the 2004 Chaplin / Mathews Initiative Plan. Part of this plan was to redesign the secondary street systems to enhance vehicular movements in the area. In 2007, the Town acquired the subject street rights of way with the intent of rehabilitating the dilapidated streets. The streets included in the project are Oak Park Drive, Mingo Way, Cooperative Way, Thompson Street, Power Alley, and Electric Avenue.

The scope of work includes rebuilding the roads with new drainage and improving on-street parking to ensure unrestricted traffic flow. A new segment of roadway of Electric Avenue from Mingo Way to Cooperative Way will be constructed to enhance connectivity of the streets. Permanent parking and temporary construction easements have been acquired for the project and plans were completed in 2013 for construction.

Project Updates

What happened the week of October 20, 2014

  • Trees are being planted and landscaping finished
  • Pavement Markings to be installed on Parking Spaces and STOP locations
  • Additional hazardous tree removal to occur on Oak Park Drive
  • Miscellaneous concrete work to be installed

What happened the week of October13, 2014

  • Paving on Power Alley
  • Landscaping was started

What happened the week of October 6, 2014

  • Paving on Cooperative Way
  • Paving on Mingo Way
  • Paving on Thompson Street
  • Grading and compaction on Power Alley
  • Pervious parking space installation

What happened the week of September 29, 2014

  • Paving on Oak Park Drive
  • Paving on Mingo Way
  • Concrete gutter centerline to be formed and poured on Thompson Street
  • Grading and compaction on Thompson Street
  • Grading and compaction on Power Alley

What happened the week of September 22, 2014

  • Paving of Electric Avenue from Power Alley to Oak Park Drive
  • Concrete gutter centerline poured on Cooperative Way
  • Concrete formed for parking on Cooperative Way
  • Paving on one lane of Oak Park Drive
  • Grading on Thompson Street
  • Grading on Power Alley

What happened the week of September 15, 2014

  • Grading, compaction, and stone base on Electric Avenue from Cooperative Way to Oak Park Drive
  • Concrete gutter centerline formed on Electric Avenue
  • Concrete gutter centerline formed on Oak Park Drive and Mingo Way

What happened the week of September 8, 2014

  • Grading on Electric Avenue
  • Compaction and stone base places on Electric Avenue from Power Alley to Cooperative Way
  • Concrete gutter centerline formed on Electric Avenue
  • Demolition of existing pavement on Oak Park DriveDemolition of existing pavement on Mingo Way

What happened the week of August 25, 2014

  • Storm drainage pipes on Mingo Way installed
  • Storm drainage pipe on Oak Park Way installed
  • Storm drainage pipes on Electric Avenue completed
  • Grading continued on Electric Avenue
  • Rock stone base installed on Electric Avenue

What happened the week of August 18, 2014

  • Storm drainage pipe work on Mingo Way completed
  • Grading along Electric Avenue began

What happened the week of August 11, 2014

  • Storm drainage Electric Avenue continued
  • Stormwater management pond completed
  • Storm drainage on Mingo Way begins

What happened the week of August 4, 2014

  • Relocation of 8" waterline and 6" waterline along Electric Avenue
  • Installation of storm drainage pipes and drainage inlets began along Electric Avenue
  • Construction of stormwater management pond began

What happened the week of July 28, 2014

  • Clearing was conducted along Electric Avenue
  • Utility Coordination underway with potholing of utility lines to determine depths

Project Objectives

  • Rehabilitate the existing Town-owned roads by improving drainage and pavement conditions.
  • Provide safe and compliant on-street parking.
  • Provide unrestricted traffic flow.
  • Maintain Island Character by preserving specimen trees and landscaping on the project

Project Facts

  • Design Engineer: HGBD, Inc.
  • Contractor: JS Construction Services, Inc.
  • Project Start Date: July 2014
  • Expected Completion Date: November 2014

Project Map

Project Map

General Project Layout PDF icon

Project Photos:

Photo of Lagoon Road South Before Construction
Clearing along Electric Avenue
July 28, 2014
Lagoon Road Pathway Construcction Photo
Storm Drainage Installation alpong Electric Avenue - August 13, 2014
Lagoon Road Pathway Construction Photo
Installation of storm drainage pipes along Electric Avenue - August 14, 2014
Photo of Lagoon Road Pathway Construction
Stormwater management pond
August 18, 2014
Photo of Lagoon Road Pathway Construction
Grading along Electric Avenue
August 18, 2014
Photo of Lagoon Road Pathway After Construction
Electric Avenue
August 27, 2014

Photo of Lagoon Road Pathway After Construction
Rock stone base installed on Electric Avenue
August 27, 2014

Photo of Concrete Gutter Formation and Grading on Electric Avenue
Concrete Gutter Formation and Grading on Electric Avenue - September 12, 2014

Photo of Grading on Mingo Way
Concrete Gutter Formation and Grading on Mingo Way - September 17, 2014

Photo of Grading on Oak Park Drive
Concrete Gutter Formation and Grading on Oak Park Drive - September 18, 2014

Photo of Forming of New Parking on Electric Avenue
Forming of New Parking on Electric Avenue
September 18, 2014

Photo of Paving of  Electric Avenue
Paving on Electric Avenue
September 22, 2014

Photo of Compaction on Thompson Street
Compaction on Thompson Street
September 30, 2014
Photo of Compaction of Power Alley
Compaction on Power Alley
October 8, 2014
Photo of Paving of Mingo Way
Paving of Mingo Way
October 9, 2014
Photo of Paving and Parking on Cooperative Way
Paving of Parking and Cooperative Way
October 9, 2014
Photo of Paving of Power Alley
Paving of Power Alley
October 13, 2014
Photo of Paving of Thomspon Street
Paving of Thompson Street
October 13, 2014
Photo of Drainage Improvements on Thompson Street
Drainage Improvements on Thompson Street
October 21, 2014
Photo of Landcape and Retention Pond
Landscape and Retention Pond
October 21, 2014

Project Manager:

Jennifer Lyle, P.E., Assistant Town Engineeremail icon - (843) 341-4779