New Orleans Road Pathway Project

This multi-use pathway was constructed from the intersection of New Orleans Road and William Hilton Parkway and connect to the existing pathway at Compass Rose Park. The project provided a multi-use pathway down the east side (Shipyard side) of the road.  This project required an extensive amount of storm water piping down an existing ditch that when completed had the multi-use pathway constructed over it. The project also included the redesign of the driveway entrance to some of the businesses along New Orleans Road. The scope of work involved taking an existing roadway shoulder and ditch, clearing undergrowth, extending some of the storm water drain system, relocating some of the utilities as needed, grading, and installing the base and final layers of pathway materials.

Pathway Project Facts

  • Approximately 3500 linear feet of pathway comprising of asphalt, concrete pathways
  • Approximately 226 linear feet of wooden bridges
  • Installation of storm drain system along the pathway
  • Project Start Date: December 2010
  • Completion Date: May 2010

Project Area Map

New Orleans Road Pathway Project Area Map

Project Photos

Photo of New Orleans Road North Before Construction
New Orleans Road North Before Construction
Photo of New Orleans Road South Before Contrsuction
New Orleans Road South Before Construction
Photo of New Orleans Road Pathway Construction
Week of January 11, 2010
Photo of New Orleans Road Pathway Construction
Week of January 11, 2010
Photo of New Orleans Road Pathway Construction
January 20, 2010
Photo of New Orleans Road Pathway Construction
Week of January 20, 2010
Photo of New Orleans Road Drainage Construction
Week of January 26, 2010
Photo of Drainage Construction along New Orleans Road
February 12, 2010
Photo of Drainage Construction along New Orleans Road
February 12, 2010
Photo of New Orleans Road Pathway Construction
March 8, 2010
Photo of New Orleans Road Pathway Construction
March 15, 2010
Photo of paving of New Orleans Road Pathway
April 19, 2010
Photo of New Orleans Road Pathway Drainage Construction
April 25, 2010
Photo of New Orleans Road Pathway Construction
May 10 ,2010
Photo of New Orleans Road Pathwy After Construction
New Orleans Road Pathway
Photo of New Orleans Road Pathwy After Construction
New Orleans Road Pathway
Photo of New Orleans Road Pathwy After Construction
New Orleans Road Pathway
Photo of New Orleans Road Pathwy After Construction
New Orleans Road Pathway

Project Manager: Bruce Skipper email icon, Engineering Technician II - (843)341-4778