Mathews Drive - Marshland Road Roundabout

The purpose of the project is to increase safety, circulation, and the aesthetic character of the area. The scope of the project includes creating a single lane roundabout at Mathews Drive and Marshland Road, with a dedicated right turn lane from Marshland Road to Mathews Drive. This is the last phase of the Mathews Drive corridor improvement plans. The Mathews Drive South roadway and pathway improvements were completed in 2008, the Mathews Drive North pathway and roundabout at Mathews Drive and Beach City Road were completed in 2011, and the Town owned Mathews Drive Side Streets rehabilitation project was completed in 2014.

Pavement resurfacing operations on Indigo Run Drive from William Hilton Parkway (US 278 Bus.) to the roundabout at Leg O’ Mutton Road and Pembroke Drive are scheduled from April 28th through May 9th. The paving resurfacing operations will intermittently close portions of Indigo Run Drive and the roundabout at Leg O’ Mutton Road and Pembroke Drive during the daytime hours from 7 am to 7 pm.  Traffic will be controlled through the work zone via flaggers, signs, message boards, and other traffic control devices.

Project Facts:

  • Engineer: Infrastructure Consulting & Engineering
  • Contractor: The Lane Construction Corporation
  • Project Start Date: January 5, 2015
  • Expected Project Completion Date: April 10, 2015

Ariel photo of project area

Project Updates:

What’s happening the week of March 23, 2015

  • Concrete to be formed and poured for the new planted medians on Marshland Road approaching the roundabout
  • Left turn lane detour scheduled to end
  • Temporary pavement markings an signs to be installed for new roundabout
  • Removal of existing pavement on Mathews Drive coming southbound to the roundabout scheduled

What happened the week of March 16, 2015

  • Concrete formed and poured for new planted medians on Mathews Drive approaching the roundabout
  • Base and intermediate asphalt course of asphalt installed on right turn movement from Marshland Road to Mathews Drive
  • Stormwater pipe installed under Mathews Drive

What happened the week of March 9, 2015

  • Oyster shell concrete poured and completed for the remainder of the roundabout truck apron
  • Asphalt removal for new planted medians

What happened the week of March 2, 2015

  • Left turns from Marshland Road to Mathews Drive and left turns from Mathews Drive to Marshland Road became unavailable
  •  Detour for left turns from Marshland Road directed to Leg-O- Mutton Road to Gardner Drive to William Hilton Parkway or turn right onto Mathews Drive to William Hilton Parkway
  • Left turns from Mathews Drive to Marshland Road detoured to the next traffic circle at Port Royal Plaza or to William Hilton Parkway
  • Demolition of existing asphalt for the new traffic circle interior
  • Grading and Compaction for the western side of the roundabout
  • Interior concrete curb poured for the remainder of the roundabout

What happened the week of February 23, 2015

  • Concrete curb formed and poured for the right turn from Marshland Road to Mathews Drive
  • Left turn detour scheduled to begin on February 25, 2015 delayed to February 27, 2015 due to inclement weather events

What happened the weeks of February 9 – February 20, 2015

  • Grading of slopes in the northbound direction of Mathews Drive behind the new roundabout and curb
  • Existing concrete medians removed at the intersection
  • Preparation of the roundabout for the left lane detour

What happened the week of February 2, 2015

  • Concrete curb on eastern side of roundabout continued
  • Oyster shell concrete poured for eastern side of truck apron
  • Subgrade compacted, base and intermediate course of asphalt paved on eastern side of roundabout

What happened the week of January 26, 2015

  • Pathway removed on south west quadrant
  • Relocated pathway on south west quadrant formed with aggregate base
  • Concrete curb poured on eastern road edge and truck apron of roundabout

What happened the week of January 19, 2015

  • Grading and compaction for the new roadway section on Phase 1 (eastern side of roundabout)
  • Concrete curb formed for Phase 1

What happened January 5 through January 16, 2015

  • Mobilization, construction staking and layout
  • Installation of silt fence and traffic control devices
  • Pavement removal, clearing and grubbing, and backfill installed within limits of Phase 1

Construction Photos

Photo of Mathews Drive - Marshland Road Roundabout Construction
Preparation for Curbing Phase 1
Photo of Mathews Drive - Marshland Road Roundabout Construction
Concrete Curb Placed for Phase 1
Photo of Mathews Drive - Marshland Road Roundabout Construction
Concrete Truck Apron Phase 1
Photo of Pathway Preparation on South West Quadrant
Pathway Preparation on South West Quadrant
Photo of Existing Concrete Medians Removed
Existing Concrete Medians Removed
Photo of Base and Intermediate Course of Asphalt Installed on Easter Side of Roundabout
Base and Intermediate Course of Asphalt Installed on Easter Side of Roundabout
Photo of Demolition of Asphalt for Interior of Roundabout
Demolition of Asphalt for Interior of Roundabout
Photo of Truck Apron Concrete Curb Installation
Truck Apron Concrete Curb Installation
Photo of Truck Apron Oyster Shell Concrete Installation
Truck Apron Oyster Shell Concrete Installation
Photo of Concrete Curb Installation on Mathews
Concrete Curb Installation on Mathews