Shelter Cove - Palmetto Dunes Pedestrian Underpass Bridge

Project Details
Status:   Complete   Complete Icon

Project Area Map

Project Description

Replace the existing pedestrian bridge underpass, connecting public pathways of the Shelter Cove area and the Palmetto Dunes area.

Project Objectives

Construct a new multi-use pathway bridge under US 278 meeting current AASHTO standards.

Additional Documents



Projected Construction Start Date:  January 2016

Estimated Completion Date:  April 2016

Project Engineer:  Cranston Engineering

Construction Contract Awarded To:  To Be Determined

Funding Sources:  Hospitality Tax

Estimated Cost of Project:  $300,000

Project Manager:  

Jeff Buckalew email icon, Town Engineer, 843-341-4772


Project Updates
  • 4/27/2106 - Project Complete. Open for use.
  • 4/13/2016 - Construction of the new pathway bridge connecting the Shelter Cove area to the Palmetto Dunes area is schedule to be completed on April 26th.

Project Photos & Videos
  • Photo of Pedestrian Bridge After ReplacmentPedestrian Bridge After Replacment - 4/28/2016
  • Photo of Pedestrian Bridge After ReplacmentPedestrian Bridge After Replacment - 4/28/2016
  • Photo of Pedestrian Bridge After ReplacmentPedestrian Bridge After Replacment - 4/28/2016
  • View More Photos...