US 278 - Fresh Market Shoppes to Shelter Cove/ Chaplin Pathway

Project Details
Status:   Complete   Complete Icon

Project Area Map

Project Description

A new multi-use pathway along William Hilton Parkway Business (US 278) to provide a connection at the traffic signal at Queens Way in front of Hargray, continuing the on-island side of US 278 down King Neptune Drive and rehabilitation of the pre-existing pathway along Shelter Cove Lane (for approximately 1.2 miles of pathway).

Project Objectives

Construct multi-use pathways along east bound US 278 Business, connecting to existing pathways at the Shelter Cove Town Centre (near Kroger’s gas station) and at the new traffic signal at Queens Way.



Projected Project Schedule:  January 2015

Projected Construction Start Date:  January 2015

Estimated Completion Date:  May 6, 2015

Project Engineer:  Town of Hilton Head Island Engineering Division

Construction Contract Awarded To:  Atlantic Asphalt

Funding Sources:  Hospitality Tax, Hospitality Bond, Traffic Impact Fee

Estimated Cost of Project:  Approximately $1 million

Project Manager:  

Jennifer Lyle email icon, Assistant Town Engineer, 843-341-4779


Project Updates
  • 5/6/2015 - Project Complete