• Text Size:
  • A
  • A
  • A

Island Recreation Center Expansion

Project Details
Status:   Under Construction   Under Construction Icon

Project Area Map

Project Description

Design of a new gymnasium, new pool restrooms, parking, storage, and relocating three basketball courts, and improvement of the existing gymnasium.

View additional Project info at www.islandreccenter.org external link icon


Inside Rendering of Island Recreation Center Project



Projected Construction Start Date:  FY 2016

Estimated Completion Date:  Fall 2018

Project Architect:  FWA

Construction Contract Awarded To:  Fraser Construction

Funding Sources:  General Obligation Bond

Estimated Cost of Project:  $7.5 million

Project Manager:  

Julian Walls email icon, Facilities Manager, 843-342-4587


Project Updates
  • 9/25/2018 - The project continues to progress well. Site finishing’s to include parking lot pervious paving in front of Gym A. Gym B interior finishing’s underway. Completion still scheduled for mid-end of October.
  • 8/21/2018 - The project continues to progress well. Planting installation underway around the School Rd parking lot and new tennis courts. Baseball and tennis courts net rigging underway with netting planned for install next week. Outdoor basketball resurfacing continues this week. Other site finishes are on-going to include parking lot lighting, bicycle racks, and flag poles. Gym B interior finishes progressing to include floor finishes, door installs and painting. The project completion timeline is still estimated to be October of this year.
  • 6/26/2018 - The project continues to progress well. New school rd. parking lot pervious brick pavers, asphalt and striping work continues through the first week of July. Gym A certificate of occupancy issued and temporary trailers scheduled for removal. Gym B brick veneer and storefront glass and aluminum progressing. The medal roofing has been completed. The projects expected completion timeline is still estimated to be September/October of this year.
  • 5/25/2018 - The project continues to progress well. New school rd. parking lot drainage and grading complete. New pool bath, pool office bld. and pool storage bld. scheduled for contractor punch list and final cleaning this week. New pool fencing and shade canopy scheduled for next week. Gym A bath accessories, gym floor curing pre-finished doors and door hardware scheduled for completion this week. Bleachers and contractor punch list scheduled for next week. Still on track for C of C for the week of 5/21. The projects expected completion timeline is now estimated to be September/October of this year.
  • 4/23/2018 - The project continues to progress well. Gym A occupancy is still scheduled for the 1st week in May. The old tennis courts have been demolished making way for the new parking lot on School Rd. The new pool bath house and pool office building are expected to be completed by the end of this month. Gym B's exterior is moving along to include roofing, brick veneer and storefronts. The projects expected completion timeline is now estimated to be September/October of this year.

Project Photos & Videos