Wiley Road Roadway Improvements

Project Details
Status:   Under Construction   Under Construction Icon

Project Area Map

Project Description

The paving of 850 feet of an existing dirt road. Paving will be permeable asphalt to allow infiltration of rainwater and is intended to greatly reduce surface runoff.

Project Objectives

Provide a paved roadway and shoulders that accommodate the safe and efficient movement of motor vehicles, emergency vehicles, and bicycles, and address right of way drainage and mitigate storm water runoff issues.

Projected Project Schedule:  February 2018 through May 2018

Projected Construction Start Date:  February 2018

Estimated Completion Date:  May 2018

Project Engineer:  Infrastructure Consulting Engineers

Construction Contract Awarded To:  Quality Enterprises, USA

Funding Sources:  Road User Fee

Estimated Cost of Project:  $323,206

Project Manager:  

James Cook email icon, Engineering Project Manager, 843-341-4778

Project Updates
  • 3/20/2018 - Reservoir and filter stone is in place. Paving is expected between 3/21 and 3/31, weather permitting.

Project Photos & Videos
  • Photo of Filter Stone
    Filter Stone - 3/12/2018
  • Photo of Reservoir Stone
    Reservoir Stone - 3/5/2018
  • Photo of Wiley Road Before Construction
    Wiley Road Before Construction - 2/21/2018
  • View More Photos...