• Text Size:
  • A
  • A
  • A

Office Park Road / Pope Avenue / New Orleans Road Intersection Improvement Project

Project Details
Status:   Under Construction   Under Construction Icon

Project Area Map

Project Description

Expansion and realignment of the existing signalized intersection. The New Orleans Road approach will be widened to include two left turn lanes, one straight through lane, and one right turn lane. The Office Park Road approach will be widened to include a left turn lane, straight through lane, and right turn lane. The Pope Avenue south (beach) bound approach will be widened to include a left turn lane to New Orleans Road, two through lanes, and a right turn lane to Office Park Road. The project construction also includes geometric improvements at the intersection of Office Park Road and Greenwood Drive by lengthening turning storage lanes for vehicles entering and exiting Office Park Road at Greenwood Drive.

Project Objectives

Improve vehicular and pedestrian traffic capacity, safety, and conveyance.

Additional Documents



Projected Project Schedule:  February through June 2018

Projected Construction Start Date:  February 2018

Estimated Completion Date:  June 2018

Project Engineer:  Infrastructure Consulting and Engineering

Construction Contract Awarded To:  Quality Enterprises USA, Inc.

Funding Sources:  TIF

Estimated Cost of Project:  $3,400,000 (including design and property acquisition)

Project Manager:  

Jennifer Lyle email icon, Assistant Town Engineer, 843-341-4779


Project Updates
  • 6/4/2018 - Media Release - Traffic Interruptions Continue at Office Park Road and Greenwood Drive
    Traffic interruptions at Office Park Road and Greenwood Drive will continue on Monday, June 4, 2018 through Saturday, June 8, 2018, due to ongoing road construction. Temporary lane closures on Office Park Road may prohibit turning movements from Greenwood Drive onto Office Park Road at times from 7:00 a.m. to 7:00 p.m. more information...
  • 6/4/2018 -
    • Traffic switch to Phase 2 (work on north side of intersection) occurred on 5/9/18. Traffic signal heads relocated to southern mast arm and traffic on Office Park Rd and New Orleans Road shifted to south side of the intersection.
    • CVS Office Park driveways are being modified to accommodate road improvements. The driveway on Office Park Road closest to Pope Ave will be turned to a right in / right out only access. The TD Bank New Orleans Road driveway closest to Pope Avenue is being modified to a right in / right out access only and will be closed until June 9, 2018. Storm drainage is being installed along access points to CVS and TD Bank.
    • Traffic Control / X-walks modified for construction phasing.
    • Work continues on Greenwood Drive intersection improvements. Concrete curb and gutter installed on June 1, 2018.
    • Construction on critical storm drainage crossing of Pope Avenue at night (from TD bank to CVS) occurred the week of May 29 - June 2. Temporary lane closures occurred on Pope Ave on May 29 - June 2.
    • Reclaimed waterline in median of Pope Ave to was offset on 5/29/18 & 5/30/18 to accommodate storm drainage crossing and new mast arm foundations. Leftturn lane on Pope Ave to New Orleans Road will be closed temporarily during the day.
  • 5/4/2018 - Media Release - Traffic Interruptions Continue at Office Park Road and Greenwood Drive
    Traffic interruptions at Office Park Road and Greenwood Drive will continue through Saturday, May 12th , due to ongoing road construction. Temporary lane closures on Office Park Road will restrict turning movements from Greenwood Drive onto Office Park Road at times from 7:00 a.m. to 7:00 p.m. more information...
  • 5/4/2018 - Media Release - Traffic Interruptions to occur at Office Park Road, Pope Avenue and New Orleans Road - May 7 through May 9
    On Monday, May 7th, motorists should expect to encounter traffic interruptions at the Office Park Road, Pope Avenue and New Orleans Road intersection, while crews transition traffic control for the next phase of construction. Law enforcement officers will direct traffic through this intersection from approximately 2:00 p.m. to 4:00 p.m. while the electrical connections to the traffic signal are replaced. more information...
  • 4/26/2018 - Media Release - Traffic Interruptions - Office Park Road and Greenwood Drive
    Traffic interruptions on Office Park Road and Greenwood Drive will continue through Saturday May 5th, 2018. The traffic interruptions will occur while construction crews continue curbing and pavement work on Office Park Road and Greenwood Drive. more information...

Project Photos & Videos
  • Photo of New Travel Lane - New Orleans Base Pavement
    New Travel Lane - New Orleans Base Pavement - 3/23/2018
  • Photo of New Pathway and Travel Lane - Office Park Rd
    New Pathway and Travel Lane - Office Park Rd - 3/23/2018
  • Photo of Intermediate Pavement Installation
    Intermediate Pavement Installation - 3/15/2018
  • View More Photos...