Coligny Area Roadway Improvements

Project Details
Status:   Open for Bid   Open for Bid Icon

Project Area Map

Project Description

(Nassau Street, South Forest Beach, Lagoon Road Extension, Pope/Lagoon Intersection-Traffic Signal)

Various Roadway Improvements – new traffic signal at Pope-Lagoon, improved turn lanes on Pope Avenue, Extending Lagoon Road from Pope Avenue to Tanglewood Drive.

Project Objectives

To improve traffic and pedestrian capacity and safety and support other public projects and economic development in this initiative area.



Projected Project Schedule:  

Design/Permitting: Summer 2015 - Spring 2016

Projected Construction Start Date:  Fall 2016

Estimated Completion Date:  Spring 2017

Project Engineer:  Thomas & Hutton Engineering Company

Construction Contract Awarded To:  To Be Determined

Funding Sources:  TIF

Estimated Cost of Project:  $4,200,000

Project Manager:  

Jennifer Lyle email icon, Assistant Town Engineer, 843-341-4779


Project Updates
  • 9/30/2016 - A Request for Proposals for the Nassau Street Redevelopment and Pope Avenue and Lagoon Roads intersection Projects was issued with a solicitation deadline of October 27, 2016.
  • 9/16/2016 - An Invitation for Bids for the South Forest Beach Drive Pathway and Tanglewood Drive Pathway Improvement Projects was issued. The solicitation deadline is October 12, 2016.
  • 7/15/2016 - Request for Proposal for Coligny Redevelopment Project was issued including both the road projects (Nassau Street, Lagoon Road Extension, Pope/Lagoon Extension, South Forest Beach) and the park project. The solicitation deadline is August 25, 2016.
  • 6/15/2016 - The Planning Commission approved application for Public Project Review for additional road improvements including a fully signalized intersection at Pope Avenue and Lagoon Road.