Coligny Area Roadway Improvements

Project Details
Status:   Under Construction   Under Construction Icon

Project Area Map

Project Description

(Nassau Street, South Forest Beach, Lagoon Road Extension, Pope/Lagoon Intersection-Traffic Signal)

Various Roadway Improvements – new traffic signal at Pope-Lagoon, improved turn lanes on Pope Avenue, extending Lagoon Road into new park and adding on-street parking.

Pathway Reconstruction along Tanglewood Drive, and a new pathways along the Oceanside of South Forest Beach Drive from Coligny Beach Park to Tanglewood Drive.

Related CIP Project:

Lowcountry Celebration Park (Coligny Area Redevelopment Initiative)

Project Objectives

To improve traffic and pedestrian capacity and safety and support other public projects and economic development in this initiative area.

Additional Documents


 
Hilton Head Island - Coligny Area Park & Transportation Projects
Public group
Join Facebook Group
 
Subscribe to Updates
e-subscription iconTo sign up for email updates, enter your email address below.


Projected Project Schedule:  

Design/Permitting: Summer 2015 - Spring 2016

Projected Construction Start Date:  September 2018

Estimated Completion Date:  June 2019

Project Timeline
Pope Avenue Resurfacing Draft Paving Schedule

Project Engineer:  Thomas & Hutton Engineering Company

Construction Contract Awarded To:  Quality Enterprises

Funding Sources:  TIF

Estimated Cost of Project:  $4.82 million

Project Manager:  

Jennifer Lyle email icon, Assistant Town Engineer, 843-341-4779


Project Updates
  • 5/17/2019 - Work is proceeding with the goal of completing all work on Pope Avenue prior to Memorial Day weekend, which starts Friday May 24, 2019. We are working with the S.C. Department of Transportation to schedule removal and replacement of the sections of rippled or wavy surface pavement.

    What Happened the Week Ending May 17, 2019

    • Continuation of stormwater installation on Nassau Street to the pond on the new Park.
    • Paved Pope Avenue turn lanes and medians.
    • Paved of Pope Avenue at Coligny Circle.
    • Did base paving of Lagoon Road widening at Pope Avenue.
    • Installed concrete curb and gutter along the new Park and parking lot entrance.

    What's Happening the Week of May 18, 2019

    • Weekend (May 18-19) - Grading and preparation for new parking spaces for the beach parking lot adjacent to Pope Avenue.
    • Weekend (May 18-19) - Stormwater installation on Nassau Street from Pope Avenue to the pond on the new Park.
    • Completion of the asphalt paving on Pope Avenue turn lanes.
    • Installation of the drainage structure at Nassau Street and Deallyon Avenue. Continuation of the stormwater infrastructure on Nassau Street from Pope Avenue to the pond on the new Park.
    • Possible milling and paving of the remediation areas of asphalt paving on Pope Avenue northbound right (outside) lane from Cordillo Parkway to Executive Park Drive and Pope Avenue southbound right (outside) lane from Coral Sands to Nassau Street (to be completed between 7 p.m. and 9 a.m.).
    • Grading and possibly paving of the new parking spaces for the beach parking lot.
    • Conduit boring for wiring of new traffic signal at Pope Avenue and Lagoon Road intersection.
    • Installation of traffic signal poles at the Pope Avenue and Lagoon Road intersection.
    • Continuation of stormwater infrastructure on Nassau Street at Deallyon Avenue and from Pope Avenue towards the pond on at the new Park.
    • The new Park contractor will begin clearing trees along Nassau Street for the new Park.
  • 5/10/2019 - Work is proceeding with the goal of completing all work on Pope Avenue prior to Memorial Day weekend, which starts Friday May 24, 2019. The sections of rippled or wavy surface pavement will be removed and replaced. We are working with the contractor to schedule that work.

    What Happened the Week Ending May 10, 2019

    • Continuation of stormwater installation on Nassau Street to the pond on the new Park.
    • Installation of concrete curb and gutter on Pope Avenue and Lagoon Road intersection in the medians and by the gas stations.
    • Pavement leveling at Pope Avenue and Lagoon Road.
    • Milling on Pope Avenue northbound from Lagoon Road to Nassau Street.
    • Asphalt paving on Pope Avenue turn lanes and medians (near completion) and northbound lanes from New Orleans Road to Sea Pines Circle.

    What's Happening the Week of May 11, 2019

    • Weekend - Surface paving on Pope Avenue and Lagoon Road intersection (Friday, May 10 through Saturday, May 11 from 7 pm to 9 am).
    • Completion of asphalt paving on Pope Avenue turn lanes and medians.
    • Conduit boring for wiring of new traffic signal at Pope Avenue and Lagoon Road intersection.
    • Installation of traffic signal poles at the Pope Avenue and Lagoon Road intersection.
    • Continuation of stormwater infrastructure on Nassau Street at Deallyon Avenue and from Pope Avenue towards the pond on at the new Park.
    • Possible milling and paving of the remediation areas of asphalt paving on Pope Avenue northbound right (outside) lane from Cordillo Parkway to Executive Park Drive and Pope Avenue southbound right (outside) lane from Coral Sands to Nassau Street.
  • 5/6/2019 - Parking Summary for the Coligny Area Improvements:
    There will be a net increase of approximately 129 spaces in Summer 2020 after the LowCountry Celebration Park is completed. In Summer 2019, there will be a decrease in parking spaces while construction is underway on the park. However, the parking lot entrance is expected to be re-opened on Pope Avenue by Memorial Day weekend 2019.
  • What Happened the Week Ending May 3, 2019

    • Detector signal loops installed on Pope Avenue at Lagoon Road and repairs to signal loops on Pope Avenue at Cordillo Parkway.
    • Continuation of stormwater installation on Nassau Street to the pond on the new Park.
    • Installation of concrete curb and gutter on Pope Avenue and Lagoon Road intersection.
    • Completion of stormwater infrastructure installation on Pope Avenue at Lagoon Road (by the gas stations).
    • Leveling paving at Pope Avenue and Lagoon Road.
    • Asphalt paving of both southbound lanes from Sea Pines Circle to Office Park Road minus a small segment at Office Way in the right lane.
    • Asphalt paving of southbound right (outside) lane from New Orleans Road to Coral Sands. Asphalt paving of northbound left (inside) lane from Nassau Street to New Orleans Road.
    • Asphalt paving of southbound left (inside) lane from New Orleans Road to Nassau Street – Scheduled for Friday – Sunday, May 3 – May 5. Hours are 7 pm to 9 am.

    What's Happening the Week of May 6, 2019

    • Asphalt paving on Pope Avenue. Here is the tentative schedule:
      • Asphalt paving on Pope Avenue turn lanes.
      • Asphalt paving on Pope Avenue northbound from New Orleans Road to Sea Pines Circle.
      • Remediation of asphalt paving on Pope Avenue northbound right (outside) lane from Nassau Street to Executive Park Drive and Pope Avenue southbound right (outside) lane from Coral Sands to Nassau Street.
    • Completion of concrete landings and median curbing at Pope Avenue and Lagoon Road.
    • Continuation of stormwater infrastructure on Nassau Street.
  • 5/2/2019 - There were issues with last night's paving operations resulting in segments with an uneven surface and poor ridability. We are working with the contractor to correct this. Paving will continue tonight, although time and place is subject to change due to corrective work needed. Paving hours will still be 7 pm – 9 am. Please use extra caution if driving through the work zone.
    • Day work continues on the Pope Avenue concrete medians and the sidewalks at Lagoon Road, as well as wiring for the new traffic signal at Pope and Lagoon.
    • A small section of Nassau Street remains closed to through traffic (only during daytime work operations) near the loading driveway behind Circle Center where crews are installing storm water infrastructure.

Project Photos & Videos
  • Photo of Curb / Gutter Formation and Grading at Park Entrance
    Curb / Gutter Formation and Grading at Park Entrance - 5/16/2019
  • Photo of Paving Pope Ave at Coligny Circle
    Paving Pope Ave at Coligny Circle - 5/16/2019
  • Photo of Milling of Northbound LanePope Avenue Near Lagoon Road
    Milling of Northbound LanePope Avenue Near Lagoon Road - 5/10/2019
  • Photo of Median Curbing at Pope Avenue and Lagoon Road
    Median Curbing at Pope Avenue and Lagoon Road - 5/7/2019
  • Photo of Pond Outfall Installation
    Pond Outfall Installation - 5/7/2019